Five finished screens do not necessarily make a usable release. A purchasing manager may be able to open a request and click Approve, yet have no way to return an incorrect amount or identify the corrected version. Count completed decisions, not screens.
Define one end-to-end outcome
For the first release, an employee submits a purchase request, the responsible manager decides, and the employee sees the result. Accounting integration, budget dashboards and multi-level approval are out. Returning a request is in, because it is part of normal purchasing rather than a rare enhancement.
| Starting condition | Action | Observable outcome |
|---|---|---|
| Authorized employee has a complete request | Submit | One reference is issued; the right manager sees it |
| Amount needs correction | Manager returns it with a reason | Employee sees the reason; status is not approved |
| Returned request has been corrected | Employee resubmits | Manager sees the current version and the earlier decision |
| Unrelated user is signed in | Requests access | Case details and attachments are not disclosed |
| Manager approves the correction | Employee checks status | Approval clearly applies to the corrected version |
These criteria describe behavior rather than implementation. The GOV.UK guide to user stories provides useful background on describing the user, need and intended outcome.
Have the client perform the test
Prepare role-specific test accounts and fictitious records. Let a client representative operate the system without step-by-step coaching. Record the observed outcome, evidence, pass or fail, owner and retest date. An interface that works only while its designer points at each button has taught you something worth documenting.
Separate a defect from a new decision
If the agreed return reason never reaches the employee, acceptance failed. If a finance director now wants a second approval step, discuss a scope change. The distinction protects both sides: the client can require the promised workflow, and the team can price newly discovered work without arguing over what “almost finished” means.
Follow a single test through to the evidence
In a fictitious test case, an employee submits request 42 with the wrong amount. The manager returns it with a reason. The employee corrects the amount and the manager approves the revision. Confirm that the employee sees approval for the revised request, the return reason remains in the history and the manager's decision is stored against the corrected amount. Attach a test export or a screenshot containing only fictitious data.
If the employee still sees the status of the original version, record the observation with a fix owner and retest date. After the fix, repeat the scenario from the original submission and compare the final state in the employee and manager accounts.